Today we backfilled the hole with gravel and brought in about 6000 gallons of water. The guys also set up the equipment pad and moved the filters, pumps, and heater into position (third time's a charm! Sorry, fellas!)


If you're picky about where you want your plumbing lines to run, make sure you have your backhoe handy, ladies. Diane helps out here by digging a 35-foot ditch to the equipment pad to keep the plumbing from running under the proposed pool house/dressing area.